Taiyo Kogyo Column

Example of temporary construction: How to realize a temporary retaining wall with short construction period and long durability without using large sandbags

Japan is a country of rain and mountains. Landslides of large and small scale occur frequently in many places, and earth retaining works and temporary standby retaining wall construction have become routine tasks for local governments. Landslides that occur on mountain roads and forest roads essentially require construction work such as concreting the slope, but it is not easy to take immediate and thorough action with the time and budget given to local governments. Therefore, temporary construction work is generally carried out, but there are challenges here as well.

 

Large sandbags are often used in construction projects because of their high cost advantages, and transporting and installing them requires heavy equipment such as large trucks and cranes to be brought to the site. However, forest and mountain roads are often too narrow to accommodate such heavy equipment. In addition, the service life of large sandbags is said to be about three years at most, and repair work is often required at many locations where they have been in place for a long time after temporary installation. The “Continuous Box Type Steel Frame” solves these problems, shortening the construction period by its high workability regardless of the site, and realizing stability and long-term durability at the same time by its excellent integrity. The “Continuous Box Type Steel Frame” makes it possible to create a temporary standby retaining wall with strong integrity. This paper introduces this construction method in detail with examples with photographs. We hope that civil engineering project personnel in public offices and local governments will take a look at the contents of this report.

What is Continuous Box Type Steel Frame?

ここで紹介する事例では、すべて連続箱型鋼製枠を採用しています。

連続箱型鋼製枠は、亜鉛メッキ鉄線製の格子状のパネルをコイル連結したカゴ(鋼製枠)を複数接続した構造で、分割・延長・屈曲させて設置できます。鋼製枠の内側に不織布を張り、現地発生土や砕石、栗石等を中詰めすることで、連続した土堤を簡単・迅速に構築でき、土留め、堤防嵩上げ工、仮締切工等に使用できます。

Related information: Download Slope Protection Resources

Outline and Features of Continuous Box Type Steel Frame "MAXWALL

Maxwall uses lattice-like panels made of galvanized iron wire, which are durable enough to withstand use for about 10 years, making it suitable for temporary construction over a long period of time. Because of its high durability and the fact that it does not require any filling material, Maxwall was introduced in the areas affected by the Great East Japan Earthquake as a temporary earth embankment and earth retaining system for raising embankments and embankments, and has been installed in coastal areas using locally generated soil and concrete rubble recycled from rubble due to the shortage of materials such as crushed stone. The following is a brief introduction of its outstanding features.

Feature 1: High stability

Large sandbags often used for temporary construction are not connected and not integrated, making them vulnerable to external forces and unstable, such as collapsing if the load is concentrated in one place. Maxwall, with its continuous steel frame, can withstand more than four times the external force (approximately 16 kN) of large sandbags, demonstrating its high stability.

Feature 2: Watertightness due to soil continuity

The inner frame (the red frame in the figure below) is not covered with non-woven fabric, and the continuous filling material such as sand and soil ensures high water sealing performance that cannot be achieved with large sandbags.

Feature 3: High durability and can be used as a long-term temporary installation

While large sandbags can be used for only about 6 months to 3 years, Maxwall has a durability of more than 10 years on land and in the soil, and about 5 years in areas where seawater splashes. In the Great East Japan Earthquake, Maxwall was used for a long period of time in coastal areas as a temporary construction material for revetments and earth retaining works.

 

Feature 4: Any filling material can be used, including earth, sand, crushed stone, and locally generated soil.

It can be used not only for earth and sand, but also for crushed stone and chestnut stone, and can also be used as a residual concrete formwork.

 

Feature 5: Can be stacked, split, extended, and bent

The standard size (one unit) consists of a series of ten 1-meter cubic steel frames (cells), which can be freely divided, extended, and bent to suit the scale of construction and site conditions. It can also be stacked, allowing it to flexibly adapt to the shape of the site.

 

Feature 6: 25% shorter construction period than conventional large sandbags

It does not require skilled labor and can be installed by five people for approximately 40 meters per day. This is an approximate 25% reduction in construction time compared to large sandbags.

Example of temporary standby retaining wall

Here are some examples of actual use of “Maxwall” continuous box-type steel frames as temporary standby retaining walls on mountain roads and forest roads.

Miyagi Prefecture Rim Township slope construction

 

In this case, immediate countermeasures were required at a site where landslides were frequently occurring due to typhoons and other factors. Initially, large sandbags were considered, but the following issues raised the need for a different solution.

  • Difficulty in transporting and installing large sandbags to sites with narrow widths
  • The need to finish the project in a short period of time, as the narrow site cannot be sealed off for a long period of time.
  • Landslides occur frequently, so even temporary structures must have a certain level of durability and integrity.

Maxwall was the solution to this problem.

 

A 1-meter pocket was created and installed between the Maxwall and the slope, assuming the amount of collapsed sediment. Despite the slope collapse during a major typhoon in September 2015, sediment was able to accumulate on the back of the retaining wall, thus preventing sediment from flowing out onto the road.

Client Community Development Division, Ohgo-cho Town Hall, Miyagi Prefecture
Construction Location En no Sato, Ogo-cho, Kurokawa-gun, Miyagi Prefecture
Site Situation slope (e.g. of embankment)
Type used MW-1350
Filling Material Locally generated soil
Quantity used 3 units (30m)
Number of tiers 1 tier
Construction Date August, 2015
Construction time About 1 day

 

Yamagata Prefecture Landslide Prevention

Client Shinjo River Office, Tohoku Regional Development Bureau, Ministry of Land, Infrastructure, Transport and Tourism
Construction location Steep slope, Tsuruoka City, Yamagata Prefecture
Type used MW-1000
Quantity used 12 units, 96m

 

Wakayama Prefecture Disaster Recovery

Client Tanabe City Hall, Wakayama Prefecture
Construction location Tanabe City, Wakayama Prefecture, Japan
Type used MW-1350
Quantity used 6 units, 60m

 

Osaka Prefecture Disaster Recovery

Client Ibaraki City Hall, Osaka Prefecture
Construction Location Mountains, Ibaraki City, Osaka
Type used MW-1000
Quantity used 8 units, 80m

Related information: Download Slope Protection Resources

Inquiry about Continuous Box Type Steel Frame

We have introduced a new option to solve conventional problems in earth retaining works such as temporary standby retaining walls, using the continuous box-shaped steel frame Maxwall.

Although Maxwall is a temporary material, it can withstand long-term use and shorten the construction period. In addition, it is an excellent construction method that can reduce overall costs because it does not require special skilled workers or skilled laborers.

It has been widely adopted by local governments, especially as a solution for sites where land is limited or a high service life is required. To learn more about Maxwall or to contact a representative, please visit the following link

> Taiyo Kogyo Corporation Continuous box-type steel frames “Maxwall

  • TOP>
  • Taiyo Kogyo Column>
  • Example of temporary construction: How to realize a temporary retaining wall with short construction period and long durability without using large sandbags